The first crowd on Catskill's new Main Street sidewalks will be kids in costumes going from shop door to shop door on Saturday afternoon, October 31. That's six days before the official ribbon cutting on November 6.
That order matters because of what the project actually rebuilt. Most of the streetscape work went into the strip of concrete between the curb and the storefront door. A door-to-door holiday puts that whole strip to use at once, all along the street.
From Halloween weekend to the December First Friday
The Village of Catskill scheduled final paving for the week of October 19. It posted a notice calling paving "the milestone" that would "end major construction on Main Street." Here is what follows.
| Date | Event | Where | Hours |
|---|---|---|---|
| Fri, Oct 30 | Catskill Emo-Ween | Avalon Lounge, 29 Church St | 8 p.m. to midnight |
| Sat, Oct 31 | Village of Catskill Halloween Festivity | Main and Bridge Streets | Noon to 3 p.m. |
| Sat, Oct 31 | Boo at the Zoo, last day of the season | Bailiwick Animal Park, 118 Castle Rd | Noon to 5 p.m. |
| Sun, Nov 1 | Upstate Composers Orchestra | Avalon Lounge | 7:30 to 9:30 p.m. |
| Fri, Nov 6 | First Friday Fall Festival and Main Street Ribbon Cutting | Head of Main Street | 5 to 8 p.m., ribbon at 5:30 |
| Sat, Nov 7 | Honor A Veteran ceremony | Historic Catskill Point | 10 a.m. |
| Fri, Dec 4 | Next First Friday | Main and Bridge Streets | Monthly |
During paving week the Village banned parking on Main Street from Thompson Street to Dutchman's Landing, from 6 a.m. to 7 p.m. each weekday. It sent drivers to side blocks, nearby lots and the Dutchman's Landing lot. The notice ended with "We are almost there!!!" and the Halloween schedule picks up from there.
What the crews were actually building toward
Village Board President Natasha Law described the streetscape phase to WRGB CBS6 in September. Crews were replacing about 85% of the sidewalks and curbing, planting 49 new trees, putting in new streetlights, and adding parking meters that take coins and cards. The Times Union listed pedestrian bump-outs as part of the scope, along with lead service line replacement and the removal of combined sewer overflows.
Most of that is visible. What isn't visible is how long it took to reach this point. Work began in May 2025 with water and sewer lines, paused for winter in November 2025, and started again at the end of March 2026. Law said the underground work from Church Street up to Summit Avenue was finished by late May 2026. Central Hudson then came in to lay new gas lines, and the streetscape phase began the same month. Her statement to WRGB also gave a sense of what crews found underground:
"The Village of Catskill was established in 1806, and we are working with infrastructure dating back that far. While we do our best to plan for what is underground, there have been many surprises along the way including finding historic tunnels and even old wooden water lines."
This is where Halloween comes in. WRGB's September report looked at the temporary drop of roughly 4 inches between torn-up sidewalk sections and existing doorways. Law explained that the gap was an interim construction stage. She said final paving, curbing, tie-ins and poured concrete sidewalk finishing would "bring all grades back up to properly meet access points." Trustee Vice President Peter Grasse III told the station the old sidewalks had been a "huge liability" for years. WRGB reported that construction was expected to finish by the end of October.
An afternoon of children walking up to every participating storefront puts weight on the joints between new concrete and old thresholds, block after block.
Saturday, noon to 3
The Village of Catskill Halloween Festivity runs on Main Street and Bridge Street from noon to 3 p.m. on October 31. It includes trick-or-treating at participating small businesses and a haunted house at the Police Station. If paving wrapped up on schedule, this daylight Saturday will be the first time the finished street sees a full weekend crowd.
Bridge Street also has something new since the last Halloween. Josie's Coffee Shoppe, a Saugerties café, opened its second location at 51 West Bridge Street in early September, NEWS10 reported. Owner Vanessa Piazza started with a soft-opening menu of coffee, lattes and pastries. She told the station she would be "starting small, settling in and adding all the little pieces that will make this place feel like Josie's."
The village event ends at 3 p.m., which leaves time for a second stop. Boo at the Zoo at Bailiwick Animal Park runs until 5 p.m.:
- 10 trick-or-treat stations with costumed characters
- Free face painting
- Costume contest at 3 p.m.
- Headless Horseman appearance at 4 p.m.
- Pony rides, a food truck and visits with the animals
Bailiwick calls the event the final day of its 2026 season before it closes for winter. Tickets are sold at the door, with no reservations, and it is cash only. There is an ATM on site. Families who want both events will be tight on time. The costume contest starts at 3 p.m., the same hour the village festivity ends.
For adults, the Halloween weekend starts the night before. Avalon Lounge on Church Street hosts Catskill Emo-Ween on October 30 from 8 p.m. to midnight, with a live set by The Story Boys. On Sunday, November 1, the Upstate Composers Orchestra plays there from 7:30 to 9:30 p.m.
Friday, November 6: the official version
Six days later the Village marks the finished street with the First Friday Fall Festival and Main Street Revitalization Ribbon Cutting. The ribbon cutting is at 5:30 p.m. at the head of Main Street, between Catskill Chocolate Co. and Loomie's Luncheonette. Main Street will be closed from upper Main and Water Street to the red light from 5 to 9 p.m. The listing calls the festival a celebration of "the completion of the major infrastructure project and the renewed beauty of our historic merchant district."
The lineup:
- Live music from Lex Grey and The Urban Pioneers
- Balloon animals by Mr. Twisty
- A Puppy Pub Crawl
- A pumpkin-rolling contest
- A silent disco
- 50/50 raffles
- Merchant passports and swag bags. Buying a signature drink enters your name in a door-prize drawing for a merchant gift card.
Merchants and restaurants will also run specials and discounts. It doesn't replace the usual monthly event. First Fridays Catskill normally runs on the first Friday of every month from 5 to 8 p.m. The organizers post updates on the Catskill Happenings Instagram page. This month the street gets closed to traffic and a ribbon gets cut. The next First Friday after that is December 4.
The morning after, and what still comes later
On Saturday, November 7, at 10 a.m., Greene County holds its Honor A Veteran ceremony at Historic Catskill Point. This year it honors retired Lt. Col. Barbara Caldara as the 2026 Greene County Veteran of the Year. Catskill Point is a short walk down from the ribbon at the other end of the same street.
The parking meters are the one piece still unsettled. The Village plans dual meters serving 150 paid spaces, according to an earlier Daily Gazette HudsonValley360 report. At the time of that report, the Village had not signed a contract for new meter poles, pole costs had risen after tariffs, and paid parking could start after the rest of the streetscape work. Check posted signs before assuming the old rules still apply.
The work also continues beyond Main Street. Law told WRGB that once Main Street is complete, the Village will put out bids to continue the clean water effort on the east side of the village. Once Main Street wraps up, the next round of cones moves to the east side of the village.
If you own a building on the rebuilt stretch of Main Street, new sidewalks, trees and streetlights out front change how your property shows. CENTURY 21 New West Properties is based right here in Catskill and has watched this project block by block. Request a Free Property Valuation, and we'll show you what the finished street means for your address.