Nearly all of the money spent digging up Catskill's Main Street went underground. Village Board President Natasha Law puts the Main Street portion at roughly $7.6 million. That breaks down to $2,395,727.91 for water, $2,918,633.74 for sewer and about $2.3 million from the state's Downtown Revitalization Initiative for everything above the pavement. HudsonValley360 reported a larger DRI figure of $2.8 million for the above-ground phase, and neither source explains the difference, so this post uses Law's breakdown. The new parking meters, the one piece of the project people will use with their own hands every week, have a state-approved budget of $98,000. They are also expected to be the last thing installed.
Here is where the street stands as of early October. Above ground, the work wraps up this month. The meters will follow a little later. The schedule ended up that way because of how each piece was bought.
Where the $7.6 Million Went
| Component | What it replaced | Amount |
|---|---|---|
| Water | Water mains and lead service lines | $2,395,727.91 |
| Sewer | Sewer mains and combined sewer overflows | $2,918,633.74 |
| Streetscape, DRI-funded | Sidewalks, curbing, trees, streetlights, meters | About $2.3 million |
| Meter equipment, within the DRI share | 75 dual meters for 150 spaces | $98,000 approved |
The village rolled three underground jobs into one dig so Main Street wouldn't have to be torn up three separate times. Crews replaced the water and sewer mains, pulled out aging lead service lines and eliminated the combined sewer overflows that can send untreated sewage into local waterways during heavy rain. The village dates to 1806, and Law said crews kept running into infrastructure nearly that old, including historic tunnels and old wooden water lines.
Law's own timeline shows how much of the past two seasons went to work no one will ever see. Ground broke in May 2025. The street was patched for the winter in November and reopened for digging at the end of March 2026. Underground water and sewer work from Church Street up to Summit Avenue was finished by late May 2026. Central Hudson then arrived to lay all-new major gas lines, and the streetscape phase began that same month. All of that is now buried for good. The streetscape is the part residents will actually see.
What Shows Up When the Cones Come Off
The above-ground phase replaces about 85% of the sidewalks and curbing. It also adds 49 new trees, new streetlights and new meters that take both coins and cards. The Times Union reported pedestrian bump-outs as part of the same package. As of September 24, more than 70% of the new sidewalks were in place.
Sections of Main Street now sit roughly 4 inches below doorways and driveways. Law described that drop as a temporary result of removing old sidewalks and laying sub-base. She said final paving, curbing, tie-ins and finished concrete will bring the grades back up to meet entrances.
The finish line depends on who you ask. In the Times Union's September 25 story, Law said the work was on track for mid-October. CBS6 reported a day earlier that construction was expected to be done by the end of October. No ribbon-cutting date has been announced. The work this week is still on curbs and sidewalks. A Village notice dated October 2 described sidewalk demolition on Main Street's east side, running from Greene Street north toward the courthouse. Starting Sunday at 9 p.m., parking is banned on the west side of the street, the odd-numbered side, from Phōs down to 261 Main Street so crews can pour curbs.
Why the Meters Are Last
The sewer pipe and the sidewalk concrete came from contractors working on site. The meters had to be ordered from a manufacturer, and that is the one step where a small village's plans depended on companies far from Catskill.
The village included 75 dual meters covering 150 paid spaces in its DRI application. Law said the old meters can no longer be maintained, but the board wanted to keep the same style. "We like them because it keeps the small-town-charm look in the village," she told HudsonValley360.
From there, the order hit three problems in a row:
- The supplier closed. The board had a favorable quote of $90,875.04 from POM Incorporated of Arkansas. The 50-year-old company ceased operations in February, which cost the village a two-month pause while it sought state approval to switch vendors.
- The replacement supplier was in Canada. After running out of domestic options, the village turned to MacKay Meters in Nova Scotia, which gave a spring quote of $97,225. "We like to buy American-made products as much as possible," Law said, "but parking meters, even ones that accept (debit and credit) cards, are becoming a thing of the past."
- The tariffs landed on the poles. After the August 22 increase in U.S. tariffs on Canadian goods, the cost of the poles the meters mount on rose from $13,125 to $19,687.50. That pushed the order past the state's $98,000 limit.
The fix keeps part of the purchase in the village. On MacKay's recommendation, Catskill will source the poles from a local company and import only the meters from Canada. The village is weighing two local quotes and may hire the same business to do the installation. If the new poles still come in over budget, the old ones stay. "They are pretty universal," Law said. "Paint will bring them back to life." As of September 25, no pole contract had been signed. Law said the $98,000 cap will not be breached and taxes will not go up to maintain paid parking. Paid parking may not start until a short while after the rest of the project wraps. "I'm sure no one will mind," she said.
Parking Until Then
The Village's posted rule hasn't changed. Metered parking runs Monday through Saturday, 9 a.m. to 5 p.m., and meters are exempt on Sundays and legal holidays. Tickets issued since January 1, 2025 are paid at the Town of Catskill, 439 Main Street, or left in the Town Court drop box at the police station.
When a block is closed, Greene County Economic Development's construction page lists these off-street lots:
- Summit Avenue to Church Street: County Lot off Union Street, the lot next to Return Brewing Outpost, and the Town Lot off Brandow Alley
- Church Street to William Street: the lot next to the Greene County Office Building, the Water Street County Lot, public parking across from the Community Theater, and the Catskill Senior Center Lot off Thompson Street
- Bridge Street to Bronson Street: the Court House Lot off Hill Street
Each evening, the village posts the next day's work schedule on its website, the Village of Catskill Facebook page and the Catskill Downtown Public Improvements Facebook page. Recorded daily updates are available by calling Village Hall and pressing 2. Village Hall's number is 518-943-3830. Businesses expecting deliveries during a closure can call Field Inspector Mike McGrath at 518-291-7373.
The Businesses That Stayed Open Through It
The project has drawn comment from local business owners: AfterGlow Tanning co-owner Jennifer Simmons and Fox Den Beauty Bar owner Ashley Stutts both spoke to the Times Union about it. Law said the village put up signs at entry points saying Main Street businesses remain "fully open and accessible." She added that direct tax abatements weren't structurally feasible without shifting the burden onto other village taxpayers.
Some owners are planning around the finished street. Kira Goldfarb of Cat on the Corner shared her hopes for the project: "It will be beautiful when it's done, and hopefully next summer will be more pleasant." Tom Illari of Catskills Collectibles leased the storefront next to his antique shop so he could expand.
"I'm investing in the end product here - in what Main Street is going to be like. This stuff needed to be done, and there's never a convenient time to do it."
Both Illari and Goldfarb said communication from the village has improved since the early days of the project.
What Gets Dug Up Next
Main Street is only the first phase. Law said that once it's complete, the village will put the clean-water work on its east side out to bid. No bid date has been announced.
The rest of the village's DRI award goes to individual projects rather than one street. The state's May 8, 2026 announcement includes $186,000 for an ADA-accessible small craft launch on West Main Street, $432,000 for a new wayfinding and signage system, $1,588,000 to transform Bridge Street Theatre at 44 West Bridge Street, and $1,469,000 to renovate the historic Catskill Public Library at 1 Franklin Street. The library will preview its renovation at a free 125th-anniversary event on Saturday, October 24. Josie's Coffee Shoppe opened its second location at 51 W. Bridge St. in early September, on the same street as the theater.
If you own a building on or near Main Street and want to know how the finished streetscape affects what it's worth, CENTURY 21 New West Properties has been watching the work block by block alongside you. Request a Free Property Valuation, and Natasha Witka will walk you through what the new street means for your address.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.